As of Wednesday, December 7th
BCC TENTATIVE REMODEL TIMELINE
Drywall work and electrician work continues for next week or so... DONE
Ceiling light fixtures installed by... 12/9/2011
Concrete Sealant application to be put on... Week of 12/19
Painting in Lobby completed by... DONE
Carpet in Lobby installed by... 12/16/2011
Parking Lot poles and light fixtures... 12/16/2011
Welcome Desk... By middle December
Dimmer Switch, 10 wk l/t; ETA is middle December... 12/20/2011
Theater Seats ETA... 12/20/2011
Theater Seats Install time is up to 9 days... 1/5/2012
Carpet in Sanctuary installed after Seats are installed... Middle January 2012
Acoustically Panels... 3rd or 4th week of January 2012
As of Sunday, September 18th
Worship Center
- Electricians have been focusing on installing new electrical that needs to be completed before first concrete pouring.
- Wood framing is being prepared for concrete pouring.
- Their will actually be three stages of Electrical work and concrete pouring, starting from the back of existing platform through the Worship Center towards the back of the Worship Center.
Parking Lot
- Has been prep, fill placed where needed and properly graded.
- Light Pole electrical and concrete curbs will be installed in the next few weeks.
Timeline
- Worship Center - All Worship Center concrete pours and electrical work should be completed by September 21st and then the concrete requires 7 additional days of cure time.
- Lobby (our front entrance) – should be completed first week of October.
- Parking lot should be completed by mid October.
- Worship Center ceiling staining and electrical work should be completed by mid November.
- Goal is to have all construction completed by Thanksgiving.
- New Worship Center seating, again, had a 20 week lead time and is currently scheduled for delivery mid December.