February 12-18... We are 99% finished! Furniture has been ordered for the Lobby and sound panels are completed.
February 5-11... We are in! The sound panel material is in and will be finished soon; carpeting has been delivered and will also soon get finished.
January 29 - February 4... We are in! The sound panels will be finished as soon as the material is delivered; carpeting will get finished too.
January 22-28... The cross was hung and the organ was brought into the worship center, and this week anticipate sound system being hooked-up.
January 15-21... Carpeting installation on the Worship Center platform continues; finishing-up maple trim work; working on low voltage wiring for sound system.
January 8-14... Carpeting installation in the Worship Center continues; installation of locks, handles, etc.; finishing-up trim work; continue working on sound panels; lighting board/electrical dimming package is hooked-up and operational.
January 1-7... Carpeting installation in the Worship Center continues, electrical continues, and working on sound panels.
December 25-31... Worship Center chair installation finished, carpeting installation in the Worship Center continues, lighting control panel/dimmer installation continues, and wood trim work installation is finishing up.
December 18-24... The Worship Center chairs were delivered and installation began, carpeting installation in the Worship Center began, lighting control panel/dimmer installation continues, and wood trim work installation began.
December 11-17... The parking lot lights were installed and are working (come to the Living Nativity to see first hand), sealer was applied to the Worship Center floor, electricians are installing dimmer pack, and carpet installation continues.
December 4-10... The hallways in the back were painted, parking lot lights were delivered and are scheduled for installation, and carpet installation continues.
November 27 - December 3... The electricians hung new light fixtures, painting continued, and started with carpet removal in the back of the church and will be working their way up to the front.
November 20-26... They did woodwork and trim finish. The carpet will be going in on Monday and new lights will be hung in and rewiring done in the Worship Center.
November 13-19... The painting started, they began building the new Welcome Center, and the doors for the Worship Center were delivered and are in the process of being installed.
November 6-12... The lights were rewired and they continued with taping and mudding of
the sheetrock.
October 30 - November 5... The front doors are open for use, sheetrocking is nearing completion, they continue with electrical work, and light poles for the parking light are on order.
October 23-29... This week the Worship Center wall panels were framed and sheetrocking them this week. Also, we are still awaiting the arrival of the parking lot light poles.
October 16-22... This week the walls for what was Room 104 have been taken down, ramp has been sheet rocked, and the Worship Center ceiling was cleaned and sealed.
October 9-15... This week the demo was completed, farming in walls for the Worship Center began, and next week they will be sheet rocking.
October 2-8... This week they finished the second lift of the parking lot and painted it, demo of Room 207 was completed, and demo of the lobby continues.
September 25 - October 1... The concrete for Worship Center floor and the ramp were poured. The parking lot its first lift and the second one will be done next week.
September 18-24... The the first and second stages of concrete are done for the Worship Center platform and ramp. In the parking lot concrete was poured for the light poles, curb, and gutters too. Final grading of the parking lot this week and asphalt is schedule, weather permitting, for Wednesday and Thursday. Which means tentatively we should start using the parking lot on Sunday, October 2nd.
September 11-17... The parking lot continues to be worked on and they are getting close to pour the first stage of concrete in the Worship Center.
September 4-10... As you will notice when you drive in or by the church, the parking lot has been started; as well as, they are on schedule to begin pouring the concrete in the Worship Center. Also, demo has started in Room 207 and in Room 104 the door opening for the ramp cut out of the brick.
August 28th - September 3rd... The demo work continues as jack-hammering was done to the concrete floor and stage, tear down begins in the library area, and early stages to start on the parking lot expansion.
August 21st - 27th... The demo work has begun and work continues to proceed forward! Half of it is done as carpet has been torn out, saw cutting of the Worship Center floor, removal of concrete, and demolition of smaller areas.
August 14th - 20th... VANMAN Construction Supervisor was here meeting with Steve and dropping off some equipment for work to start on Monday.
August 7th - 13th... The final building plans were approved and the City of Buffalo issued the permit.
July 31st - August 6th... A variety of equipment was moved to the gym, we removed the pews from our Worship Center, and found $8.55 in change buried in the cushions (money went to the Building Fund).